Timeline (so far)

February
2/14/16: First time we saw the Rome model home. Happy Valentine's Day!
2/16/16: Met with SR to talk about how to really get the ball rolling.

March
3/7/16: signed contingency contract
3/16/16: wiring meeting
3/18/16: current house went on the market
3/20/16: removed contingency because we signed an offer for our house!
3/21/16: color meeting
3/21/16: flooring meeting

April
4/18/16: pre-construction meeting
4/25/16: ground breaking

June
6/16/16: pre-drywall meeting

Tenative
7/26/16: estimated project completion
 8/1/16: estimated settlement